# Time and material (T&M) ticket

> Start with a 30-day trial, then Starter at $99 a month (up to 3 active jobs) or Pro at $249 a month (unlimited jobs). Your subs and owners don't need a paid seat.

Build it in minutes. Create an account to download. The extra work on one page, the way the field gets it signed: what was done and under whose direction, labor by company and trade, equipment hours, materials, and lines for the owner’s representative to sign. Quantities only, never prices.

## What is a T&M ticket?

A record of the labor, equipment and materials used on work outside the contract, written the day the work happens and signed by the owner’s representative. It is the evidence behind a time-and-material change order.

## Should a T&M ticket carry prices?

No. It records quantities: hours, units and equipment time. Prices belong on the change order the ticket supports, under the contract’s rates. A ticket carrying a number the owner’s rep did not agree to is one they decline to sign.

## Why get it signed the same day?

Quantities agreed the day the work happened are rarely argued later. A ticket assembled at the end of the month from memory is an assertion, and the hours on it are the first thing disputed.

## Why is standby its own column?

A crew on site that could not work is a different cost from a crew working. Added together, the whole number gets argued. Kept apart, each can be priced under the contract.

## The guide behind it

[Construction Daily Reports and T&M Tickets](https://buildcontrol.group/learn/construction-daily-reports-and-tm-tickets). What a daily report should record, why every day belongs on it, and how a T&M ticket ties to the same day and gets signed.

## How to download

Fill in the form on the page and watch the preview. To get the PDF, create an account; the document is saved to a job in your account, named after the project.

General information, not legal advice. Your contract decides how extra work is directed, noticed and priced, and a signed ticket does not replace the written notice your contract may require.