Build it in minutes. Create an account to download. A change order the way a general contractor sends one: a cover letter with the scope and the total, and a worksheet with every line, the insurance and the overhead and profit. You enter your own prices.
The AIA G701 is the change order form published by the American Institute of Architects. The owner, the architect and the contractor sign it, and it states the change in the contract sum and the contract time. It fits jobs built on an AIA contract with an architect administering it.
A simple change order, like the one this page makes, carries the same essentials: the work, the price, the time and the signatures. It fits jobs with no architect administering the contract, subcontract changes, and owners who want it on one page. If your contract calls for the G701, use AIA’s form and attach this worksheet as the backup for the price.
AIA and G701 are trademarks of the American Institute of Architects. The form on this page is BuildControl’s own and is not affiliated with AIA.
Who it is between, the project, a number and a date, the scope of the change, the price with the lines behind it, the markup, what it does to the contract time, how long the price holds, and a signature. This form prints a cover letter and a worksheet with all of them.
What your contract allows. Most contracts set the overhead and profit percentage, some set one rate for your own work and another for subcontracted work, and insurance is often its own line. Read the change order clause before you type a number.
Say what it does to the schedule every time. Under most contracts a change order that is silent on time can be read as agreeing there is none. If the work needs days, ask for them in the same change order.
Before the work starts. Work done on a verbal OK is the hardest money to collect. If the owner directs the work before the price is agreed, get the direction in writing and track the cost as you go.
RFI vs. Change Order: When Does an Answer Cost Money?. The difference between a request for information and a change order, the pivot point where a clarification becomes a cost, and why "answered" is not "closed."
Fill in the form on the page and watch the preview. To get the PDF, create an account; the document is saved to a job in your account, named after the project.
General information, not legal advice. Your contract decides the markup, the notice and who signs. Read its change order clause before you send one.